UBC Brock Commons Tallwood House Project

Project Owner

UBC PROPERTIES TRUST

Architect

ACTON OSTRY ARCHITECTS INC.

General Contractor

URBAN ONE BUILDERS INC.

Completion Date

SPRING 2017

Location

VANCOUVER, BRITISH COLUMBIA

Builder

SEAGATE MASS TIMBER INC.

Structural Engineer

FAST + EPP

Completed in 2017, Brock Commons Tallwood House is an 18-storey hybrid mass timber student residence on the University of British Columbia’s Vancouver campus. At the time of completion, it was one of the tallest mass timber buildings in the world, built on a concrete foundation and cores with glulam columns and CLT floor panels. The timber structure was completed in just 66 days.

Each 9,500 sq ft floor plate, made up of 29 five-ply CLT panels delivered on three trucks, was hoisted into place using the BRGN Plate lifting system. Lifting plates secured to the top of each panel allowed quick crane rigging attachment and release. Once the crew was up to speed, cycle times consistently came in under six minutes per panel.

Structural engineering for the project was provided by Fast + Epp, with mass timber installation by Seagate Mass Timber.